OK, here we go! Rollout Run 4: GO to power up the MPPU(Mini Portable Purge Unit).
---------- Post added at 03:12 AM ---------- Previous post was at 03:05 AM ----------
As long as there won't be any more rain, they'll roll tonight.
---------- Post added at 03:20 AM ---------- Previous post was at 03:12 AM ----------
GO to transfer MLP power to MLP 0 Level generator power.
---------- Post added at 03:23 AM ---------- Previous post was at 03:20 AM ----------
Safety walkdown is complete, no discrepancies noted.
---------- Post added at 04:06 AM ---------- Previous post was at 03:23 AM ----------
Rollout forecast: Winds 8-12 kts, 10% precip, 0% lightning.
---------- Post added at 04:12 AM ---------- Previous post was at 04:06 AM ----------
GO open the crawlerway gates.
---------- Post added at 04:15 AM ---------- Previous post was at 04:12 AM ----------
CT jacked within 2" of MLP, GO to start configuring VAB platforms.
---------- Post added at 04:19 AM ---------- Previous post was at 04:15 AM ----------
Well ahead of schedule, shotting for 2300L-2330L first motion out of the VAB.
---------- Post added at 04:26 AM ---------- Previous post was at 04:19 AM ----------
Would like observers on station no later than 2300L.
---------- Post added at 04:32 AM ---------- Previous post was at 04:26 AM ----------
Observers now on the mounts in the VAB in about 15 minutes, 2245L. Seems like the crane crew will not be ready by then, but they'll do their best.
---------- Post added at 04:55 AM ---------- Previous post was at 04:32 AM ----------
Ready to jack up the MLP to clearance height.
---------- Post added at 05:25 AM ---------- Previous post was at 04:55 AM ----------
Currently jacking the CT to clearance height. Rollout should start shortly.
---------- Post added at 05:26 AM ---------- Previous post was at 05:25 AM ----------
Ready to propel!
---------- Post added at 05:28 AM ---------- Previous post was at 05:26 AM ----------
GO to start propelling to the pad! Standing by for first motion!
---------- Post added at 05:31 AM ---------- Previous post was at 05:28 AM ----------
First motion logged at 0331:51 GMT!
---------- Post added at 09:06 AM ---------- Previous post was at 05:31 AM ----------
So far the rollout is progressing nicely. Atlantis should be hard down at the pad shortly before dawn at KSC if there are no unexpected stoppages along the way.
---------- Post added at 10:10 AM ---------- Previous post was at 09:06 AM ----------
Now just outside the pad A gate.
---------- Post added at 10:22 AM ---------- Previous post was at 10:10 AM ----------
Now moving up the pad ramp.
---------- Post added at 10:54 AM ---------- Previous post was at 10:22 AM ----------
Now atop the pad A hardstand, moving over the flametrench.
---------- Post added at 11:12 AM ---------- Previous post was at 10:54 AM ----------
Almost in place.
---------- Post added at 11:14 AM ---------- Previous post was at 11:12 AM ----------
NASA TV has resumed their STS-132 rollout coverage.
---------- Post added at 11:19 AM ---------- Previous post was at 11:14 AM ----------
And the CT has stopped. Now preparing to jack down the MLP onto the mounts for hard down.
---------- Post added at 12:14 PM ---------- Previous post was at 11:19 AM ----------
The MLP was logged as hard down at 6:03 am EDT which ends the rollout at 6 hours and 31 minutes.
---------- Post added at 04:04 PM ---------- Previous post was at 12:14 PM ----------
RSS rotation to MATE position in work.
---------- Post added at 04:33 PM ---------- Previous post was at 04:04 PM ----------
RSS rotation to MATE is complete.