SOURCE OF ARTICLE: http://www.nasaspaceflight.com/2009...processing-targets-for-atlantis-final-flight/

The first of what is scheduled to be the final three Launch Site Requirements Reviews (LSRRs) for the Space Shuttle Program (SSP) has been completed by managers at the Program Requirements Control Board (PRCB) for the STS-132 mission - the 32nd and final “scheduled” flight of orbiter Atlantis, due to launch in May 2010.

Flight Specifications:
In all, STS-132 will be the 132nd flight of the Shuttle Program and the 34th shuttle flight dedicated to construction and outfitting of the International Space Station. The 11+1+2 day flight of Atlantis will utilize External Tank 136, Reusable Solid Rocket Motor set 111, Solid Rocket Booster BI set 143, and operational software OI-34.

The primary payload for the mission remains the Russian Mini-Research Module 1 (MRM-1) and Integrated Cargo Carrier – Vertical Lightweight Deployable (ICC-VLD) pallet. The MRM-1 will be mounted toward the aft of the payload bay while the ICC-VLD will be berthed in the center for both launch and reentry.


A23.jpg



SSME's Removal
index.php
 
Last edited:
STS-132 Crew Patch

Here's a preview of the STS-132 crew patch - the patch for what is currently planned to be Atlantis's final flight.

www.collectspace.com/sts132_patch

I have to say, I like this one! :thumbup:
 
Last edited:
I believe this is the crawler moving to the MLP in advance for booster stacking.
index.php
 
STS-132 NOT to be affected by STS-131's slip, although they only have 6 days to play with.

Also, Atlantis also undergoing SSME installation, to be completed next week.
 
mmmmmmm, maybe.
 
ET-136 arrived at KSC 3/1/10
SRB Stacking underway
MRM-1 arrived at KSC
Atlantis rollover to VAB April 12th

index.php


index.php
 
Upcoming key STS-132 processing dates:

MRM-1 transfer from SPACEHAB Facility to SSPF - April 2.
MRM-1 loading into Payload Canister ------------ April 5.
Payload Canister transfer to LC-39A ------------ April 15.
Atlantis rollout to LC-39A ---------------------- April 20.
 
Last edited:
A great video showing photos of MRM-1's preflight processing:

[nomedia="http://www.youtube.com/watch?v=iog40I3chSc"]YouTube- Rassvet - Russian Mini-Research Module[/nomedia]
 
Atlantis has been attached to its ET and SRBs.

[nomedia="http://www.youtube.com/watch?v=WuQmo7WrCEw&playnext_from=TL&videos=AhJljZ6-txE&feature=sub"]YouTube- STS-132 Atlantis Attached to ET and SRB's[/nomedia]
 
That's a video of ET/SRB mate(S0003), not Orbiter/ET mate(S0004). Besides Atlantis have not yet been mated to the ET. Latest report is that they're still doing the aft soft-mates.

Ah crud, just released. Thanks!
 
Watch those KSC cams, For the last time ever Atlantis will rollout to the Pad at 8 PM Tonight.

---------- Post added 04-20-10 at 01:25 AM ---------- Previous post was 04-19-10 at 10:10 PM ----------

Rollout delayed due to weather. 6 p.m EDT rollout 4/20

---------- Post added at 07:47 PM ---------- Previous post was at 01:25 AM ----------

One lands from a mission, another one goes to pad for her mission.
Atlantis for the final time ever will rollout in a little over 2 hours to Pad LC39A.

Atlantis arrived at KSC April 9th, 1985. Atlantis leaves KSC April 20th, 1985.

Rollout expected at 6 p.m. Weather is again a threat.
 